Walker Road at Willow Creek Is Scheduled to Reopen December 1. The Rest of the Rebuild Runs Years Longer.

October 29, 2026

West of 173rd Avenue, Walker Road dips down to cross Willow Creek and climbs back out. Washington County calls that dip unsafe because it limits how far ahead drivers can see. The same stretch has never had real bike lanes or continuous sidewalks. Since August 3, that low spot has been a construction pit. Crews are pulling out the old culvert so the road can be rebuilt 8 to 10 feet higher.

The full closure between NW 174th Terrace and NW Cambray Street is scheduled to end December 1. That's about a month away. For anyone who has spent the fall detouring up to Cornell Road, it's the date that matters most right now. Walker Road won't be finished on December 1, though. The reopening is one marker in a corridor rebuild the county has been working through in lettered phases for ten years, and the next stretch of disruption is already on the calendar.

What December 1 Ends, and What It Doesn't

The county's July 24 announcement lists three goals for the Willow Creek work. The new, larger culvert should help the creek stay healthier, let wildlife cross safely under the road and move water through more easily. Raising the road takes out the dip, so drivers can see farther ahead and react sooner. In its September road roundup, The Cedar Mill News added that the culvert should also improve storm flow and lower flood risk.

While the closure lasts, cars are sent onto signed detours via Cornell Road, and cyclists are routed along Autumn Ridge Drive. Neighborhood streets near the closure are open only for local access, walking and biking. The Cedar Mill News reported that local law enforcement would be watching those streets. That rule ends when the barricades come down.

The culvert closure is only one part of a bigger project. Phase 3 of the Walker Road program covers everything from 173rd to 185th Avenue. Its project page lists what the finished road will have:

  • Five lanes, with two travel lanes each way and a continuous center turn lane
  • Bike lanes and sidewalks
  • A new traffic signal at 178th Avenue and Cambray Street
  • Upgraded storm drainage and street lighting
  • Some sound walls, plus landscaping

The county is also coordinating this work with Tualatin Valley Water District waterline upgrades and with Beaverton's North Transmission Line Intertie project. The expected finish date for Phase 3 is June 2028, and the estimated cost is $28.5 million. Funding comes from the county's Major Streets Transportation Improvement Program, the City of Beaverton and utility reimbursements. The September 30 update said bridge work was still underway, with construction noise expected from 7 a.m. to 7 p.m., Monday through Saturday.

So December 1 restores the through route. The work zone stays for another year and a half.

Ten Years, Eight Letters

Washington County runs all of this as one program and labels each piece with a letter. Seen together on the county's Walker Road Projects overview, this fall's closure is a midpoint. Construction on Walker or a nearby connector began in 2016 and has run for most of the years since.

Phase Segment Construction dates Status
A, Walker Road Phase 1 Schendel Avenue to 173rd Avenue June 2016 to July 2017 Complete
B, 158th Avenue Walker Road to Merlo Station March 2017 to January 2019 Complete
C, Jenkins Road 158th Avenue to Murray Boulevard May 2019 to December 2020 Complete
D, Walker Road Phase 2 Butner Road to Schendel Avenue May 2023 to September 2025 Complete
E, Walker Road Phase 3 173rd to 185th avenues July 2026 to June 2028, expected Under construction
F, Walker and Murray intersection Walker Road at Murray Boulevard April 20, 2026 to fall 2028, expected Under construction
G, Walker Road Phase 4 Park Way to 123rd Avenue Summer 2027 to fall 2030, expected In design
H, Walker Road Phase 5 123rd Avenue to west of Highway 217 To be determined Future

Four phases are done, two are under construction and two haven't started. The longest break came between Phase C, which ended in December 2020, and Phase D, which started in May 2023. The break after Phase D was much shorter. It ended in September 2025, and Phases E and F both started in 2026. The two phases still to come, G and H, cover the segments from Park Way toward Highway 217.

The Walker and Murray Work Doesn't Stop for Winter

When the Willow Creek closure ends, the busiest active work zone will be the intersection at Murray Boulevard. The Oregonian/OregonLive described it in late August as swarming with construction crews, with large pipes piled along the road and an excavator digging near Cedar Mill Creek.

The county's intersection project page lays out the final design. Each of the four approaches gets dual left-turn lanes and a dedicated right-turn lane. Murray gets a third southbound lane from south of Butner Road through the Walker intersection. That lane becomes a dedicated right-turn lane at Bowerman Drive. Crews are also replacing two bridges over Cedar Mill Creek and two culverts on Walker between Far Vista and Park Way. The estimated cost is $44.9 million, and the expected finish is fall 2028.

The September 30 update said crews were wrapping up their in-water bridge work for the winter. That deadline is set by the calendar. The annual in-water work window runs from July 15 to September 30, the only stretch of the year when crews may work directly in the creek, which protects fish and wildlife. Work out of the water goes on. Expect temporary lane shifts, construction noise during the day and some nighttime work. Roads stay open with at least one lane in each direction. The bike lane situation has changed since August, when the right lanes and bike lane on Walker near Murray were closed. The county now says bikes may share the lane with cars during construction. New bike lanes will go in across the project area once work is finished.

Willow Creek, Cedar Mill Creek and north Johnson Creek all sit in the path of current work, and the in-water window confines creek work to midsummer each year.

Summer 2027 Is the Next Pinch Point

Here are the published dates in order, from this winter through 2030:

  1. December 1, 2026: The full Walker Road closure between 174th Terrace and Cambray Street is scheduled to end.
  2. Spring 2027: TriMet expects to finish its remodel of the Beaverton Transit Center.
  3. Spring 2027: Right-of-way acquisition for Phase 4 is expected to wrap up, and design is expected to be finished by May 2027.
  4. Summer 2027: A closure of Walker Road east of Murray Boulevard, expected to last about a month, is planned for culvert work on north Johnson Creek.
  5. Summer 2027: Phase 4 construction between Park Way and 123rd Avenue is expected to begin.
  6. June 2028: Phase 3, 173rd to 185th, is expected to be complete.
  7. Fall 2028: The Walker and Murray intersection is expected to be complete.
  8. Fall 2030: Phase 4 is expected to be complete.

Next summer, Walker Road could have a closure east of Murray and new construction starting near Park Way, while crews are still working at Willow Creek. This winter, by comparison, should be one of the easier stretches on the corridor in a while.

The Transit Center Is Getting Its Own Overhaul

The Beaverton Transit Center at 4050 SW Lombard Avenue is TriMet's busiest. Beaverton Valley Times reports that 67,000 trips a week start, end or transfer there. The center opened in 1988 as a bus layover and transfer point. It was expanded for trains when Westside MAX opened in 1998. Today it serves seven regular bus lines, the MAX Blue and Red lines and WES commuter rail.

The remodel began in the spring. According to TriMet's project announcement, it adds larger shelters with more seating, new digital signs with audible text-to-speech, better lighting, more security cameras, more room for buses, and new ramps, tactile strips and wayfinding. Two overhead chargers will let battery-electric buses charge between runs. Beaverton Valley Times reports that TriMet has 34 of those buses in its fleet. The center stays open throughout construction, but some buses may stop in different spots as work moves along. TriMet suggests giving yourself extra time for transfers.

Bus riders on Walker get hit by both projects. TriMet's Line 59, Walker/Park Way, runs between the Sunset and Willow Creek transit centers. Its route uses Walker Road between 185th and Park Way, which takes it past the Willow Creek closure, through the Murray intersection and up to where Phase 4 starts. On the far end, Willow Creek Transit Center at 395 SW 185th Avenue connects Line 59 with MAX Blue and Red and bus lines 47, 52, 88 and 288. Line 59 riders should check TriMet's current service alerts around the December 1 reopening, when stops near the old closure could change again.

Phase 4 Is Still Being Designed

Of everything on the corridor, Phase 4 is the project that hasn't been locked in. It covers Park Way to 123rd Avenue. The county describes this stretch as running through a large commercial area and past an elementary school and several churches. The plan calls for:

  • Sidewalks and ADA-compliant curb ramps on both sides
  • Bike facilities on both sides
  • Street lighting
  • Dedicated turn lanes from Walker onto Cedar Hills Boulevard
  • A center turn lane kept from Park Way to Westfield Avenue
  • Upgraded storm drains

No new travel lanes or changes to Cedar Hills Boulevard are planned.

The most recent update on the Phase 4 project page, dated June 19, 2026, said the team was still refining the design and expected to hold an open house this fall. The county offers email updates for each phase, which are linked from the Phase 3 page and the others. If you shop along Walker near Cedar Hills Boulevard or drive through that stretch every day, the open house is the place to see the design before construction, which is expected to start next summer.

When a road will be under construction can matter as much as how it looks when it's done. Whether you drive Walker to work or you're weighing how a 2027 or 2028 work zone could shape a move, I'm glad to go through the dates with you. Get in touch with Robyn Schamberger and Let's Connect.