The highway junction east of Banks has a crash rate below ODOT's own warning threshold, and it is getting a $6 million roundabout because of the land beside it. There, Holt Homes is grading roads for the Aerts Addition, a neighborhood planned for more than 900 homes. The roundabout at Highway 6 and NW Aerts Road is that neighborhood's front door, and Holt is building it.
The connection explains the timing, the shape of the intersection and the detour you'll drive around until late February. It also explains why the work at this corner is part of a longer change to the east side of town.
Where the Detour Sends You Until February
The City of Banks set Thursday, Nov. 5 as the day Highway 6 traffic would leave the temporary bypass road and move onto the finished west, east and north legs of the roundabout. Under the city's closure notice, NW Aerts Road closes for 200 feet south of the roundabout, and nobody on foot or in a car can reach Highway 6 from that side.
If you're coming from south of the highway, the signed route goes like this:
- Head west on NW Wilkesboro Road.
- Turn north on OR 47.
- Join Highway 6 at the OR 47 interchange.
The city expects the south approach to reopen on Feb. 26, 2027. Both lanes of Highway 6 stay open throughout, and the city doesn't expect any private driveways to be affected. Aerts Road north of the highway reopens on the same schedule. That's the side you use to reach Quail Valley Golf Course, which the city's transportation plan places about 320 feet north of the junction.
The detour uses roads the city already counts on to carry traffic. The Banks Transportation System Plan classifies NW Wilkesboro Road as a county collector, while Aerts is a local road. Banks Post reported that crews would use the closure to remove the temporary bypass and build the south leg.
Why a Homebuilder Is Paying for the Roundabout
ODOT's project page puts design and construction at roughly $6 million and lists the money as "local and private funds." The private part goes back to April 2024, when the City of Banks and Holt Homes signed the development agreement for the Aerts Addition. Section 9.1 of that agreement sets out who does what at this corner. Holt agreed to:
"Design, obtain permit(s), and construct the Aerts/Highway 6 Intersection Improvement (Roundabout)."
The agreement says Holt does this "at its sole cost and expense." The city's role is coordination. It attends meetings with Washington County and ODOT and, if Holt asks, makes reasonable efforts to get the county or ODOT to acquire right-of-way.
The engineering came from the same deal. The June 2024 intersection control evaluation that ODOT reviewed was prepared by Kittelson & Associates for Holt Homes. In short, the company building the neighborhood also commissioned the study and pays to build its main entrance.
Arrangements like this explain how a town the size of Banks gets a highway project years before the state would have reached it in line. It also accounts for this fall's events. ODOT lists design in 2024 and 2025 and construction in 2026 and 2027, which lines up with the homebuilding schedule next door.
Sized for 929 Homes, Not for a Crash Record
The city approved the Aerts Addition map amendments on Sept. 10, 2024, and its master-planned development on Sept. 17, 2024. The approved plan covers 204 acres and 929 homes. For a sense of how much of it is already under way, here is the progress the city engineer reported to City Council in the Oct. 13, 2026 meeting packet, along with the newest filing on the city's pending-applications page:
| Aerts Addition phase | Latest reported status, October 2026 |
|---|---|
| Phase 1A | Nearing final punch list |
| Phase 1B | Utilities nearly complete. Final plat FP 26-02 had a notice of pending decision dated Oct. 26 |
| Phase 2 | Roads rocked, mass grading underway before winter |
The same report lists Sunset View, a separate subdivision, with its Phase 1 at final punch list and grading and roadwork under way on Phases 2 and 3. Utilities for those phases go in over the winter. East Banks will have more than one active construction site this winter. In our earlier comparison of Gaston and Banks, we looked at how this kind of new construction shapes the numbers people see when they compare the two towns.
The old intersection worked for the traffic it carried, though it was awkward to drive. Aerts traffic had stop signs and Highway 6 traffic didn't stop. The 2024 evaluation also described a large, confusing layout with an extra leg at NW Washington Avenue. The study counted 10 crashes from Jan. 1, 2017, through Dec. 31, 2021. Nine involved injuries and none were fatal. In that period the observed crash rate was 0.50, well under the 90th-percentile rate of 1.08 that marks an intersection as an outlier. The most common crashes were rear-end collisions on Highway 6 and angle crashes between eastbound highway traffic and drivers coming south on Aerts.
ODOT's reason for building a roundabout looks forward. According to the agency's project overview, keeping the stop signs or adding a signal would not handle future traffic. Either option could back up the highway and cause more rear-end crashes. The design ODOT chose is a single-lane roundabout with a separate westbound right-turn lane. The project page states the purpose plainly: safety and capacity for future growth.
How the Roundabout Handles Tractors, Trucks and Bikes
This stretch of Highway 6 sits between farmland and the Sunset Highway, so the design has to handle more than cars. ODOT says the roundabout was designed for school buses, farm equipment, trucks with trailers and oversized freight trucks. Mountable truck aprons give large vehicles extra turning room, and permitted vehicles and equipment can drive over the mountable center island. The agency's FAQ has some guidance for sharing the circle:
- Give large trucks and buses plenty of room, and don't drive next to or pass them inside the roundabout.
- If you're on a bike, you can ride through the roundabout like any other vehicle.
- You can also use the sidewalks and crosswalks at walking speed, or get off and walk your bike.
What's Left to Build on This Stretch
According to ODOT's staging plan, the remaining work is removing the temporary bypass, building the south Aerts connection, finishing the curb ramps and sidewalks on the south side, and then opening that connection. The NW Washington Avenue connection to Aerts and Highway 6 is being removed. That takes away the extra leg the 2024 study flagged as confusing.
A separate state project is also on the 2026 to 2027 schedule nearby. The Banks Highway Lighting Replacement covers the Highway 6 interchanges with OR 47 and US 26, at a design and construction cost of $1,738,310. In January, Banks Post reported that the job would replace five lights on OR 47, 11 on Highway 6 and 16 on US 26 with LEDs.
The detour also runs into the holiday season. Banks' Annual Christmas Tree Lighting is Sunday, Nov. 29, at 6:30 p.m. at Greenville City Park, 12700 NW Arbor Park Loop. If you're driving in from south of Highway 6 that evening, plan on the Wilkesboro Road and OR 47 route. Check ODOT's project page for updates before you head out. For more ways to spend a free afternoon close to home, see our post on getting onto the Banks-Vernonia Trail.
The south leg of Aerts Road is expected to reopen on Feb. 26, 2027. After that, the junction will have its full four-way layout and Washington Avenue will no longer connect to it.
If you own near Aerts Road or Highway 6 and you'd like to talk through how the Aerts Addition and the new roundabout might affect your plans, I'm glad to sit down and go over the details with you. Robyn Schamberger | Let's Connect